Value

£1 million

Size

17,500 sq ft

Duration

8 weeks

Fitness First

Value Size Duration
  £1 million 17,500 sq ft 8 weeks

Following considerable fire damage to the Fitness First in Derby, TROY were recommended to lead on the refurbishment having already worked with client-side stakeholders.

This 8 week major revamp saw the team strip out the entire facility including the flooring, ceiling, lighting and lockers. The finished result revealed a modern leisure facility putting Derby firmly on the map as one of theFitness First flagship branches. From the gallery, you can see attention to detail has not been spared and even the swimming pool has a new feature; a unique stretch BARRISOL® ceiling.

Say Hello

We’d love to hear about your story and exciting projects you have coming up.

info@troygroup.co.uk   01284 706 066